What needs to be clarified
Separate unit counts, operating intervals, placement periods and material-based drying checks by documented room zone.
Materials to prepare
- Delivery, relocation and collection records with unit IDs
- Operating logs, available hour meters and outage records
- Moisture map with methods, dates and drying modes
What to compare
Build a unit-by-room timeline; check overlaps, breaks and units. Reconcile equipment-days with logs and flag unknown intervals. Compare moisture at the same points, considering material and climate. Neither an empty tank nor collection alone establishes completion.
Possible outcome of the analysis
A reconciliation may distinguish supported and disputed intervals; technical drying adequacy remains separate from contractual placement time and the agreed charging basis.
Limits of the conclusions
A present unit need not be running. Missing logs prevent exact reconstruction; equipment-day arithmetic cannot establish dry concealed layers.